Baden Park Construction Update

Re: Lytton St. Watermain Upgrade Works – Weekly Update

May 17, 2024

This week, we will complete this phase of the installation of the new water main on Lytton Street.

Starting next week, we will continue with installation of infrastructure, but only within the project (on-site).

These works will be carried out within the project during regular hours from Monday to Friday, 7:00am to 8:00pm and Saturdays from 9:00am to 5:00pm.

The next phase of infrastructure and off-site civil works will take place in early summer 2024.

An update on expected impacts will be communicated to you with ample notice.

Thank you for your patience as we continue to work to minimize disruptions to the extent possible.

Sincerely,

Doug Sissons, APG Construction/Anthem Properties Group
Dsissons@anthemproperties.com
604-315-1211

Angus Lummis, Tybo Contracting
Alummis@tybo.ca
604-836-0272